MED-94-7.66 Culvert Replacement

Primary Service

  • Roadway Engineering

Client

  • ODOT District 3

Location

  • Sharon Township

Tasks Performed

  • Surveying
  • Basemapping
  • Culvert Design
  • Roadway Design
  • Drainage Design
  • Hydraulics

Project Description

Euthenics completed the engineering and surveying for the replacement of the existing single-span slab bridge with a 4-sided 10' x 5' reinforced concrete box culvert, with reinforced concrete headwalls, reinforced concrete turnback wingwall with the invert buried 1 foot below the flowline. The project included full-depth pavement replacement and new storm sewer conduit. SR 94 was closed to thru-traffic during construction.